This page contains information on the Freeport High School Renovation Project from January, 2015 to the present (after the successful Referendum).
Building Advisory Committee Information
Click here to view the Charge of the Committee.
Click here to view the List of Freeport High School Building Advisory Committee Members.
Meeting Agendas and Minutes
Meetings are typically held the first Wednesday of each month at the FHS Library at 7:30a.m.
Schedule
December 2, 2014 - August 21, 2014
- Design & Engineering Drawings (32 weeks)
- Bidding (4 weeks)
October 1, 2015 - December 20, 2016
- Construction of two-story addition (15months)
- Portable Rentals - 1 health, 2 math, JMG (total 4 classrooms) - 18 months
December 20, 2016 - January 1, 2017 (winter break)
- Move Kitchen & Food Court
January 15, 2017 - June 15, 2017
- Renovation of cafeteria / kitchen to art & IT
- Build out JMG, SW offices, Conference Room
Summer 2016
- Build out new STEM space
- Build out SpEd & Life Skills toilets
- Build out new nurse and faculty toilets
- Renovate student bathrooms on main corridor
- Classroom upgrades
Summer 2017
- Build out new Guidance & Commons
- Build out new Administration spaces
- Build out new Learning Labs and Learning Commons renovations
May 2017 - August 2017
- Construction of lobby entrance
Fall 2017
- Full occupancy
Updates from the Architect
Construction Progress Summary - March 2016
Construction Progress Summary - February, 2016
Construction Progress Summary - December, 2015
Construction Progress Summary - November, 2015
Updates on the Project
January, 2017
New Bus Circle Outside Addition
New Cafeteria in Addition
Hallway Leading Into New Addition
April 6, 2016
February 25, 2016
February 5, 2016
January 8, 2015
December 4, 2015
November 6, 2015